A Harvard-led study published November 16, 2026, estimates that 403 major U.S. data centers consumed approximately 82 terawatt-hours of electricity in a 12-month period. More than half of the electricity attributed to their regional power grids came from fossil fuels.

Researchers at Harvard T.H. Chan School of Public Health examined hyperscale data centers—large facilities that support cloud computing, online services and artificial intelligence. The study, published in Nature Sustainability, estimates that these sites consumed about 1.8% of U.S. electricity between May 2024 and April 2025.

The same analysis associates their demand with approximately 25.7 million metric tons of carbon dioxide. That is a modeled estimate based on the regional mix of electricity generation, not a direct measurement of emissions at each individual data center. Harvard’s November 16 announcement documents the study’s methods and limitations.

Featured photograph: Aerial view of data centers and surrounding commercial buildings near Ashburn, Virginia, photographed November 26, 2025. Theodore Christopher / Wikimedia Commons; CC0 1.0.

What the study found

Study measureEstimated resultImportant qualification
Hyperscale facilities analyzed403Not an inventory of every U.S. data center
Central annual electricity estimate82 TWhModeled for May 2024–April 2025
Electricity attributed to fossil fuelsAbout 54%Regional grid-based attribution
Associated carbon dioxide25.7 million metric tonsCentral model estimate, not directly measured facility emissions
Electricity-use scenario range68–99 TWhVaries with modeled operating conditions
Source: Guidi and colleagues, Nature Sustainability, published November 16, 2026. Estimates describe the study period, not November 2026 operations. TWh means terawatt-hours.

According to the researchers, electricity attributed to the centers came principally from natural gas (approximately 38%) and coal (approximately 15%); rounding accounts for the difference between their individual shares and the reported 54% fossil-fuel total. The share varied significantly by region.

How researchers estimated power use and emissions

Because companies do not publish consistent facility-by-facility electricity data, the team identified 403 sites using satellite imagery and other facility information. They estimated power use under different operating assumptions and combined those results with U.S. Environmental Protection Agency power-generation information to attribute associated emissions. The published paper and Harvard summary explain the approach.

The study’s 82 TWh headline is the central scenario, not an audited tally of electricity bills. Its lower and upper scenarios span 68 to 99 TWh. The research also could not determine how much electricity within each facility was used specifically for AI, as opposed to other computing services.

Four states account for more than half the demand

Virginia, Oregon, Ohio and Iowa together accounted for more than half the electricity estimated for the studied facilities. That distribution matters because a data center’s associated emissions depend partly on which generators supply its regional grid.

Exterior industrial infrastructure and cooling towers at Google's data center in The Dalles, Oregon, photographed in 2015.
Google’s data center in The Dalles, Oregon, photographed in 2015 (archival photograph, not an image of the entire state data-center sector). Photo: Tony Webster / Wikimedia Commons, CC BY 2.0.

Northern Virginia’s Loudoun County shows the scale of the industry’s local footprint. As of September 1, 2026, the county reported approximately 245 existing data-center buildings and said that data centers generated $1.2 billion in real and personal property tax revenue in fiscal 2026, representing about 39% of its overall budget. Those local tax figures describe Loudoun County’s industry footprint, not the 403-facility national study. Source: Loudoun County’s official data-center overview.

Why American communities are watching

Data-center developers and utilities must manage questions about available generation, transmission capacity, equipment, energy costs, cooling systems and land use. For people living near proposed facilities, a central question is whether new electric-system investments will change their utility bills and what emissions may accompany rising demand.

The Harvard study does not establish that a particular data center caused a household’s electricity rate to increase. It also did not directly measure health outcomes among people living near power plants. Those important questions require additional research and more detailed, publicly accessible operating data.

A larger U.S. electricity trend

A separate Lawrence Berkeley National Laboratory report estimated that all U.S. data centers consumed 176 TWh in 2023, approximately 4.4% of national electricity use. The laboratory projected a possible 325–580 TWh by 2028, depending on growth, equipment and operational efficiency.

Those broader national estimates cannot be directly compared with the Harvard study’s 403 facilities as though they measure identical populations or periods. One covers all data centers, while the other focuses on a selected group of hyperscale sites.

What remains unknown

This research provides a useful historical baseline, but it does not offer real-time data-center electricity consumption as of November 2026. New buildings, expansions, changing power sources and different operating rates could all change today’s electricity and emissions totals.

More complete disclosure of facility power demand, grid connections and the sources of electricity would help communities and policymakers distinguish projected impacts from documented ones before major development and infrastructure decisions are made.

Sources and methodology